Tasks
30 of 30 tasks
| Task | Progress | Status |
|---|---|---|
Procurement — Order & Receive Devices TSK-SBY-GUBENG-P | 100% | COMPLETED 4d late |
Installation at Site TSK-GEDANGAN-I | 100% | COMPLETED |
Procurement — Order & Receive Devices TSK-GEDANGAN-P | 100% | COMPLETED |
Procurement — Order & Receive Devices TSK-BARUT-P | 60% | IN_PROGRESS |
Procurement — Order & Receive Devices TSK-KERTOSONO-P | 100% | COMPLETED |
Installation at Site TSK-SBY-GUBENG-I | 100% | COMPLETED |
Staging & Configuration TSK-SEPANJANG-S | 100% | COMPLETED |
Procurement — Order & Receive Devices TSK-MOJOKERTO-P | 100% | COMPLETED |
Installation at Site TSK-KERTOSONO-I | 40% | IN_PROGRESS |
Procurement — Order & Receive Devices TSK-WARU-P | 100% | COMPLETED |
Procurement — Order & Receive Devices TSK-WONOKROMO-P | 100% | COMPLETED |
Staging & Configuration TSK-MOJOKERTO-S | 50% | IN_PROGRESS |
Installation at Site TSK-SEPANJANG-I | 100% | COMPLETED |
Installation at Site TSK-WARU-I | 100% | COMPLETED |
Staging & Configuration TSK-JOMBANG-S | 0% | NOT_STARTED |
Installation at Site TSK-JOMBANG-I | 0% | NOT_STARTED |
Staging & Configuration TSK-SBY-GUBENG-S | 100% | COMPLETED |
Staging & Configuration TSK-WONOKROMO-S | 100% | COMPLETED |
Installation at Site TSK-WONOKROMO-I | 100% | COMPLETED |
Staging & Configuration TSK-WARU-S | 100% | COMPLETED |
Installation at Site TSK-SBY-KOTA-I | 100% | COMPLETED |
Procurement — Order & Receive Devices TSK-SEPANJANG-P | 100% | COMPLETED |
Staging & Configuration TSK-GEDANGAN-S | 100% | COMPLETED |
Staging & Configuration TSK-SBY-KOTA-S | 100% | COMPLETED |
Installation at Site TSK-BARUT-I | 0% | NOT_STARTED |
Procurement — Order & Receive Devices TSK-SBY-KOTA-P | 100% | COMPLETED 9d late |
Staging & Configuration TSK-BARUT-S | 0% | NOT_STARTED |
Installation at Site TSK-MOJOKERTO-I | 40% | IN_PROGRESS |
Staging & Configuration TSK-KERTOSONO-S | 50% | IN_PROGRESS |
Procurement — Order & Receive Devices TSK-JOMBANG-P | 60% | IN_PROGRESS |