Project Dashboard

KAI Commuter Wilayah 8 — E-Ticketing Implementation · KAI-W8-ETICKET

10
Total Stations
0
Completed
8
Active
0
Delayed
0
Blocked
50
Total Devices
26
Installed
14
Tested
10
UAT Passed
6
Handover
4
Open Issues
1
Critical
37%Overall

Project Progress

Weighted activity-based

Planned Progress55%
Actual Progress37%
Variance-18%

BEHIND SCHEDULE

Issue Summary

4
Open
1
Critical
4
Overdue
1
Resolved

Station Summary

StationProgress
Surabaya Kota
SBY-KOTA
50%
Surabaya Gubeng
SBY-GUBENG
50%
Wonokromo
WONOKROMO
50%
Sepanjang
SEPANJANG
50%
Waru
WARU
50%
Gedangan
GEDANGAN
50%
Mojokerto
MOJOKERTO
28%
Kertosono
KERTOSONO
28%
Jombang
JOMBANG
6%
Banjar Kempit
BARUT
6%